Project Timeline

StatusMilestonesAnticipated Begin DateAnticipated End Date
CompleteProject PlanningNovember 28, 2018December 3, 2018
CompleteLoad Baseline Enterprise System and Module ConfigurationsDecember 5, 2018January 25, 2019
CompleteDevelopment Environment Build and InstallDecember 6, 2018January 28, 2019
CompleteEnterprise (HR) Staging Area (ESA) DeploymentDecember 14, 2018March 13, 2019
CompleteSingle Sign-On IntegrationDecember 14, 2018March 29, 2019
CompleteBusiness Process Mapping Pre-AwardJanuary 30, 2019March 19, 2019
CompletePrototype build PD, PT, ATMay 28, 2019June 10, 2019
CompleteESA User Acceptance TestingMarch 13, 2019August 31, 2019
CompletePrototype Review, PD, PT, AT and Project Team TestingJune 10, 2019August 10, 2019
CompleteUser Acceptance TestingJuly 16, 2019September 4, 2019
Complete/OngoingCampus TrainingAugust 28, 2019November 1, 2019
CompleteProduction Environment Build and InstallSeptember 1, 2019November 1, 2019
CompletePD, PT, AT – Go-LiveNovember 1, 2019
OngoingPD, PT, AT Enhancements and UpgradesDecember 2019
In ProcessFinancial Tracking Business Process MappingJuly 2020July 2021
Not startedFinancial Tracking Prototype buildJuly 2021
Not startedFinancial Tracking Staging Area (FSA) DeploymentDecember 2021
Not startedFinancial Tracking Prototype Review and Project Team TestingApril 2022
Not startedFinancial Tracking TrainingApril 2022
Not startedFinancial Tracking Go-LiveJuly 2022